SCHNEIDER ELECTRIC – DECARBONATION MASTERTECH France

Description:

The “DECARBONATION MASTERTECH” project concerns the reduction of energy consumption and CO2 emissions associated with the following scope: comfort heating and cooling, process cooling and compressed air.

Mission:

Turnkey for the installation and commissioning of technical equipments : Heating and Cooling Unit, Process cooling unit, air compressors, textile ducts.

Electrical technical installations: HV cell, transformer, TGBT

Project Cost

2,2 M€

Specificity :

Detail Design : 4 months
construction timeline : 6 months
Commissioning : 1 month

Mission :

Turnkey technical installations

Expertise :

Project and construction Management, Scheduling, Utilities & MEP expertise, 3D modeling.