Construction of a building with an aseptic filling unit and a Quality Control Laboratory on Merck’s Aubonne plant. Pharmaceutical classification C & D. Useful surface of 12000m².
Mission:
Design update : installations dimensioning, PID, improvement and selection of the equipment. Construction support and C&Q.
Project Cost – HVAC :
> 13 millions €
Mission :
Detail Design until C&Q
Expertise :
HVAC
Specificity :
Detail Design : 4 months Construction Period : 20 months